Ms O’CONNOR question to MINISTER for PARKS and HERITAGE, Mr DUIGAN
Minister, the Edgar Dam Strengthening Project on the Pedder impoundment inside the Tasmanian Wilderness World Heritage Area was originally announced in 2019 as a $15 million project, with construction being completed by 2022. That was in the 2019 government infrastructure pipeline. Fast forward to August of this year and both yourself and Hydro Tasmania have claimed works are complete, ahead of schedule, and under budget at $35.5 million. Do you stand by that statement?
You’ve also claimed the project was undertaken in accordance with the environmental conditions set under the EPBC, but according to RTI documents obtained by my colleague, Tabitha Badger, member for Lyons, Hydro Tasmania and the department have admitted to breaking the EPBC environmental conditions surrounding truck movements on and off site outside of the permitted times, risking wildlife. Minister, I’m sure you agree it’s important we tell the truth in life, in here, and particularly if we’re ministers of the Crown. Would you today like to correct the record because the Edgar Dam Strengthening Project was not brought in ahead of schedule and under budget?
ANSWER
Just minister for Parks?
Ms O’Connor – Energy, take your pick.
Mr DUIGAN – In terms of any interaction with the EPBC, I will take that on notice. Regarding cost and budget, the board of Hydro Tasmania is responsible for managing the Hydro Tasmania capital investment program and making final investment decisions. As with any major infrastructure project, cost estimates can evolve through the planning, design, approvals, and procurement phases as the scope is redefined in more detail, information becomes available.
The Edgar Dam upgrade had an initial budget of $21 million, which was revised early in the project’s development following procurement processes and increases in construction costs. Hydro Tasmania’s board subsequently endorsed a final investment decision based on a final project budget. My comments regarding delivery on budget and ahead of schedule reflect the project’s delivery against the budget and schedule approved through Hydro Tasmania’s final investment decision process, thereby four months ahead of schedule and under budget.