Tasmanians are awaiting a long overdue update to the estimated cost of the Macquarie Point stadium. But while some transparency from the government at this point is welcome, it’s important to understand that this new information won’t paint the full picture for the stadium’s price tag.
In the Public Accounts Committee on Friday, the government made it clear that the price that’s set to be released will not account for escalation contingencies. That means contingencies will need to be excluded from past cost estimates – which have always included such figures – to make them directly comparable with the new price.
As per evidence in an earlier hearing of the Committee on 4 February, the cost escalation contingency included in the stadium’s $1.13 billion price tag was $147.6 million. Excluding this contingency amount leaves a figure of $982.5 million as the reference point for a simple baseline comparison for any cost escalations that are announced.
Macquarie Point Development Corporation told PAC:
“The project budget is $1.13 billion. It includes the full cost related to the Stadium. It isn’t just the construction. It is the design, the commissioning, the resourcing of my team, the work that’s been done to date. It also includes escalation and contingencies.”
MPDC went on to itemise a range of stadium costs covered by the $1.13 billion price tag. That included the escalation figure of $147.6 million – or just over 15% of the other budgeted costs.
Let’s be clear – contingencies are an absolutely standard part of project budgets that are included to account for the unforeseen challenges and changes that infrastructure builds often face. This protection will be particularly important for the stadium given the known challenges with building on Macquarie Point, along with the ongoing rapid rise in construction costs.
As a point of reference, a 15% contingency is applied below to different cost levels.
| Excluding contingency | Including 15% contingency |
| $1.2 billion | $1.38 billion |
| $1.3 billion | $1.495 billion |
| $1.4 billion | $1.61 billion |
| $1.5 billion | $1.725 billion |
| $1.6 billion | $1.84 billion |
| $1.7 billion | $1.955 billion |
Whatever the new cost estimate is, the fact it will exclude contingencies means it’s the floor not the ceiling for what the stadium will cost.